- Two-stage heat recovery (wastewater heat recovery)
- One new central PLC including an operator panel in the central EMSR cabinet
- Optimized tank management for hot water, cold water, and wastewater streams
- Reduction of required steam by increasing the operating temperature in the hot water tank
Key Project Measures
- Optimization of tank management, including new PLC, visualization, and revised supply control
- Integration of existing control systems into a modern central control system
- Access to plant control from the local network and via the internet
- Expansion of wastewater heat recovery through an additional plate heat exchanger and frequency-controlled pumps
- Conversion of the caustic recovery system to reduce cooling water consumption and increase hot water temperature
- Installation of backwashing for both the new and existing wastewater heat exchangers
- Installation of additional measurement and control technology to increase data transparency and display stored data in diagrams